Laurelhill

Laurelhill is an operational 8.5 MW solar farm in Armagh City, Banbridge and Craigavon, generating since 1 March 2018. Planning permission was granted on 24 May 2016, 11 months after submission. Operator of record: BNRG Northern Power.

8.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 March 2018
Solar Photovoltaics
Technology
BNRG Northern Power
Armagh City, Banbridge and Craigavon
Authority
Northern Ireland

Planning and build timeline

Application submitted22 June 2015
Permission granted24 May 2016
11 months after submission
Operational1 March 2018
21 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Armagh City, Banbridge and Craigavon: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Laurelhill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
1.19.3 km
Solar Photovoltaics · Operational
1.39.8 km
Battery · Under Construction
5011.4 km
Solar Photovoltaics · Operational
25.712.5 km

How big is Laurelhill?

Laurelhill has a recorded installed capacity of 8.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Laurelhill?

REPD records the operator as BNRG Northern Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Laurelhill approved and built?

The application was submitted on 22 June 2015. Permission was granted on 24 May 2016, 11 months later. The site became operational on 1 March 2018, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5952.