Renewable sites › Reservoir Road (Farm AD)
Reservoir Road (Farm AD)
Reservoir Road (Farm AD) is an operational 1.1 MW anaerobic digestion plant in Armagh City, Banbridge and Craigavon, generating since 4 August 2016. Planning permission was granted on 4 August 2011, 8 months after submission. Operator of record: B and D Property Services.
Planning and build timeline
| Application submitted | 13 December 2010 |
| Permission granted | 4 August 2011 8 months after submission |
| Operational | 4 August 2016 60 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Armagh City, Banbridge and Craigavon: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Reservoir Road (Farm AD)’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 8.5 | 9.3 km |
Battery · Under Construction | 50 | 10.6 km |
Advanced Conversion Technologies · Operational | 2 | 11.8 km |
Solar Photovoltaics · Operational | 1.3 | 12.9 km |
How big is Reservoir Road (Farm AD)?
Reservoir Road (Farm AD) has a recorded installed capacity of 1.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Reservoir Road (Farm AD)?
REPD records the operator as B and D Property Services. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Reservoir Road (Farm AD) approved and built?
The application was submitted on 13 December 2010. Permission was granted on 4 August 2011, 8 months later. The site became operational on 4 August 2016, 60 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 329.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode