Renewable sites › Land at Upper Clayhill Farm
Land at Upper Clayhill Farm
Land at Upper Clayhill Farm is an operational 4.9 MW solar farm in Lewes, generating since 16 December 2015. Planning permission was granted on 18 December 2014, 2 months after submission. Operator of record: Lightsource Renewable Energy.
Planning and build timeline
| Application submitted | 14 October 2014 |
| Permission granted | 18 December 2014 2 months after submission |
| Operational | 16 December 2015 12 months after consent |
Screening a site of your own?
Lewes approves 80% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land at Upper Clayhill Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Lewes’s record on solar
Lewes has decided 5 solar farms and approved 80%, taking a median of 2.1 months. See every solar farm decision in Lewes →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 4.4 km |
Solar Photovoltaics · Operational | 7 | 7 km |
Landfill Gas · Operational | 7.5 | 7.5 km |
Solar Photovoltaics · Under Construction | — | 7.5 km |
Solar Photovoltaics · Operational | 8.2 | 10.7 km |
Solar Photovoltaics · Operational | 2.6 | 12.1 km |
Solar Photovoltaics · Operational | 5 | 12.6 km |
Solar Photovoltaics · Operational | 5 | 12.7 km |
How big is Land at Upper Clayhill Farm?
Land at Upper Clayhill Farm has a recorded installed capacity of 4.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land at Upper Clayhill Farm?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land at Upper Clayhill Farm approved and built?
The application was submitted on 14 October 2014. Permission was granted on 18 December 2014, 2 months later. The site became operational on 16 December 2015, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1198.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode