Novarly ParcelRenewable sites

Renewable sitesLand approx 75m South of 141

Land approx 75m South of 141

Land approx 75m South of 141 is an operational 20 MW onshore wind farm in Fermanagh and Omagh, generating since 1 July 2007. Planning permission was granted on 26 April 2005, 3 months after submission. Operator of record: Private Developer.

20 MW
Capacity
as recorded in REPD
Operational
Status
since 1 July 2007
Wind Onshore
Technology
Private Developer
Fermanagh and Omagh
Authority
Northern Ireland

Planning and build timeline

Application submitted3 February 2005
Permission granted26 April 2005
3 months after submission
Operational1 July 2007
26 months after consent

Screening a site of your own?

RedlineUK · £39

Fermanagh and Omagh approves 92% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land approx 75m South of 141’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Fermanagh and Omagh’s record on onshore wind

Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92%, taking a median of 20.9 months. See every onshore wind scheme decision in Fermanagh and Omagh

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
13.810 km
Wind Onshore · Operational
211.8 km
Wind Onshore · Operational
12.513.3 km
Wind Onshore · Operational
13.814.2 km

How big is Land approx 75m South of 141?

Land approx 75m South of 141 has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land approx 75m South of 141?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land approx 75m South of 141 approved and built?

The application was submitted on 3 February 2005. Permission was granted on 26 April 2005, 3 months later. The site became operational on 1 July 2007, 26 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3251.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode