Land approx 75m South of 141
Land approx 75m South of 141 is an operational 20 MW onshore wind farm in Fermanagh and Omagh, generating since 1 July 2007. Planning permission was granted on 26 April 2005, 3 months after submission. Operator of record: Private Developer.
Planning and build timeline
| Application submitted | 3 February 2005 |
| Permission granted | 26 April 2005 3 months after submission |
| Operational | 1 July 2007 26 months after consent |
Screening a site of your own?
Fermanagh and Omagh approves 92% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land approx 75m South of 141’s recorded coordinate — swap in your own postcode or coordinates.
Fermanagh and Omagh’s record on onshore wind
Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92%, taking a median of 20.9 months. See every onshore wind scheme decision in Fermanagh and Omagh →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 13.8 | 10 km |
Wind Onshore · Operational | 2 | 11.8 km |
Wind Onshore · Operational | 12.5 | 13.3 km |
Wind Onshore · Operational | 13.8 | 14.2 km |
How big is Land approx 75m South of 141?
Land approx 75m South of 141 has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land approx 75m South of 141?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land approx 75m South of 141 approved and built?
The application was submitted on 3 February 2005. Permission was granted on 26 April 2005, 3 months later. The site became operational on 1 July 2007, 26 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3251.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode