Knabs Ridge Windfarm is an operational 16 MW onshore wind farm in North Yorkshire, generating since 22 April 2008. Planning permission was granted on 4 November 2004, 6 months after submission. Operator of record: RWE npower.

16 MW
Capacity
as recorded in REPD
Operational
Status
since 22 April 2008
Wind Onshore
Technology
RWE npower
North Yorkshire
Authority
England

Planning and build timeline

Application submitted23 April 2004
Permission granted4 November 2004
6 months after submission
Operational22 April 2008
42 months after consent

Screening a site of your own?

RedlineUK · £39

North Yorkshire approves 72% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Knabs Ridge Windfarm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 5 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Yorkshire’s record on onshore wind

North Yorkshire has decided 18 onshore wind schemes and approved 72%, taking a median of 5.8 months. See every onshore wind scheme decision in North Yorkshire

Other built sites within 15 km

SiteMWDistance
Battery · Operational
3311.8 km

How big is Knabs Ridge Windfarm?

Knabs Ridge Windfarm has a recorded installed capacity of 16 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Knabs Ridge Windfarm?

REPD records the operator as RWE npower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Knabs Ridge Windfarm approved and built?

The application was submitted on 23 April 2004. Permission was granted on 4 November 2004, 6 months later. The site became operational on 22 April 2008, 42 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3147.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode