Renewable sitesKillail Farm

Killail Farm

Killail Farm is an operational 0.2 MW hydro scheme in Argyll and Bute, generating since 10 June 2021. Planning permission was granted on 8 June 2022, 43 months after submission. Operator of record: Private Developer.

0.2 MW
Capacity
as recorded in REPD
Operational
Status
since 10 June 2021
Small Hydro
Technology
Private Developer
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submitted14 November 2018
Permission granted8 June 2022
43 months after submission
Operational10 June 2021

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Argyll and Bute: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Killail Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Large Hydro · Operational
67 km
Wind Onshore · Operational
33.310.5 km
Large Hydro · Operational
812.2 km
Wind Onshore · Operational
10.813.1 km
Wind Onshore · Operational
613.2 km

How big is Killail Farm?

Killail Farm has a recorded installed capacity of 0.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Killail Farm?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Killail Farm approved and built?

The application was submitted on 14 November 2018. Permission was granted on 8 June 2022, 43 months later. The site became operational on 10 June 2021.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6746.