Renewable sites › Inverclyde Wind Farm (Corlic Hill)
Inverclyde Wind Farm (Corlic Hill)
Inverclyde Wind Farm (Corlic Hill) is operational in Inverclyde with a recorded capacity of 24 MW, and has been generating since 2021-02-20.
Planning and build timeline
| Application submitted | 2013-07-08 |
| Permission granted | 2016-05-17 34 months after submission |
| Operational | 2021-02-20 57 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Faulds Park Road- Solar PV Panlels Solar Photovoltaics · Under Construction | 0.34 | 8.8 km |
Carrochan Road, Balloch - Solar Panels Solar Photovoltaics · Under Construction | 0.18 | 13.5 km |
How big is Inverclyde Wind Farm (Corlic Hill)?
Inverclyde Wind Farm (Corlic Hill) has a recorded installed capacity of 24 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Inverclyde Wind Farm (Corlic Hill)?
REPD records the operator as BayWa r.e. (formerly Forsa). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Inverclyde Wind Farm (Corlic Hill) approved and built?
The application was submitted on 2013-07-08. Permission was granted on 2016-05-17, 34 months later. The site became operational on 2021-02-20, 57 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4200.