Novarly ParcelRenewable sites

Renewable sitesHayle Wave Hub (Test Site)

Hayle Wave Hub (Test Site)

Hayle Wave Hub (Test Site) is an operational 23 MW wave energy site in DECC (S36), generating since 1 September 2010. Planning permission was granted on 15 July 2009, 53 months after submission. Operator of record: Wave Hub.

23 MW
Capacity
as recorded in REPD
Operational
Status
since 1 September 2010
Shoreline Wave
Technology
Wave Hub
DECC (S36)
Authority
England

Planning and build timeline

Application submitted17 February 2005
Permission granted15 July 2009
53 months after submission
Operational1 September 2010
14 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in DECC (S36): the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hayle Wave Hub (Test Site)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
3.55 km
Solar Photovoltaics · Operational
7.35.5 km
Solar Photovoltaics · Operational
4.75.5 km
Anaerobic Digestion · Operational
110.1 km
Solar Photovoltaics · Operational
0.1812.6 km

How big is Hayle Wave Hub (Test Site)?

Hayle Wave Hub (Test Site) has a recorded installed capacity of 23 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hayle Wave Hub (Test Site)?

REPD records the operator as Wave Hub. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hayle Wave Hub (Test Site) approved and built?

The application was submitted on 17 February 2005. Permission was granted on 15 July 2009, 53 months later. The site became operational on 1 September 2010, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2457.