Renewable sites › Hawthorn Farm - Solar photovoltaic panels
Hawthorn Farm - Solar photovoltaic panels
Hawthorn Farm - Solar photovoltaic panels is under construction in South Derbyshire with a recorded capacity of 10 MW.
Planning and build timeline
| Application submitted | 2021-03-25 |
| Permission granted | 2022-02-22 11 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Derbyshire’s record on solar
South Derbyshire has decided 12 solar farms and approved 67%, taking a median of 4.9 months. See every solar farm decision in South Derbyshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Aston House Solar Farm Solar Photovoltaics · Operational | 20 | 2.8 km |
Rolleston Park Farm Solar Photovoltaics · Operational | 18.7 | 3.4 km |
Morton House (Marchington) Solar Photovoltaics · Operational | 6.2 | 4.6 km |
Land of Green Lane Solar Photovoltaics · Operational | 5.8 | 5 km |
Holtwood Farm Solar Photovoltaics · Operational | 5 | 7.1 km |
Somersal Mill Farm Solar Photovoltaics · Operational | 2.6 | 8 km |
Marchington Solar Farm Solar Photovoltaics · Operational | 4.3 | 8.4 km |
Toyota Solar Farm Solar Photovoltaics · Operational | 4.6 | 9.1 km |
How big is Hawthorn Farm - Solar photovoltaic panels?
Hawthorn Farm - Solar photovoltaic panels has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hawthorn Farm - Solar photovoltaic panels?
REPD records the operator as Unknown. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hawthorn Farm - Solar photovoltaic panels approved and built?
The application was submitted on 2021-03-25. Permission was granted on 2022-02-22, 11 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8856.