Renewable sitesHammar's Hill

Hammar's Hill

Hammar's Hill is an operational 4.3 MW onshore wind farm in Orkney Islands, generating since 20 September 2010. Planning permission was granted on 6 January 2009, 10 months after submission. Operator of record: Hammers Hill Energy Ltd.

4.3 MW
Capacity
as recorded in REPD
Operational
Status
since 20 September 2010
Wind Onshore
Technology
Hammers Hill Energy Ltd
Orkney Islands
Authority
Scotland

Planning and build timeline

Application submitted11 March 2008
Permission granted6 January 2009
10 months after submission
Operational20 September 2010
20 months after consent

Screening a site of your own?

RedlineUK · £39

Orkney Islands approves 93% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hammar's Hill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Orkney Islands’s record on onshore wind

Orkney Islands has decided 28 onshore wind schemes and approved 93%, taking a median of 6.2 months. See every onshore wind scheme decision in Orkney Islands

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
2.34.2 km
Wind Onshore · Operational
1.54.5 km
Wind Onshore · Operational
55 km
Wind Onshore · Operational
2.35 km
Battery · Operational
213.9 km

How big is Hammar's Hill?

Hammar's Hill has a recorded installed capacity of 4.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hammar's Hill?

REPD records the operator as Hammers Hill Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hammar's Hill approved and built?

The application was submitted on 11 March 2008. Permission was granted on 6 January 2009, 10 months later. The site became operational on 20 September 2010, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2697.