Novarly ParcelRenewable planning

Renewable planning Onshore windOrkney Islands

Onshore wind planning in Orkney Islands

Orkney Islands has decided 28 onshore wind schemes and approved 93% of them, taking a median of 6.2 months to decide. Consented capacity: 159 MW. 5 applications still awaiting a decision.

93%
Approved
26 granted · 2 refused
6.2 mo
Median decision
UK 11.5 mo
159 MW
Consented
14 MW refused
2
Appeals
2 allowed on appeal

How Orkney Islands compares

Against the 75 UK authorities with 5+ onshore wind decisions, Orkney Islands sits in the 93rd percentile for approval rate (25 points above the England average) and the 91st percentile for speed.

Decisions by year

35Approved — 2 (2011)211Approved — 1 (2012)112Approved — 1 (2013)113Approved — 1 (2015)115Approved — 2 (2019)219Approved — 3 (2021)321Approved — 1 (2023)123Approved — 1 (2024)124Approved — 3 (2025)325
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (37)

SchemeMWStatusDecided
Greentoft, Neven Point, Eday - Wind Turbines & BESS
Green Power (International) Limited · 25/203/TPPMAJ
24Application Submitted2025-06-23
Akla Wind Energy Project - Wind Turbine
Orkney Renewables Limited · 25/079/TPP
2Application Submitted2025-04-08
New Holland, Stratheast Road -Wind Turbine
New Holland Wind Llp · 24/360/TPP · 5.3 mo to decide
0.5Awaiting Construction2025-02-24
Newark, Skelwick - Wind Turbine
Distgen Limited · 24/298/TPP · 5.4 mo to decide
Awaiting Construction2025-02-13
Harbour Authority Building, St Ola - Wind Turbine
Orkney Sea Cadets · 24/299/TPP · 4.1 mo to decide
Awaiting Construction2025-02-06
Ludenhill, Lochside Road - Wind Turbine
Constantine Wind Energy · 23/295/TPP · 7.1 mo to decide
0.5Awaiting Construction2024-03-26
Work Farm, Work Road - Wind Turbines
Birsay Energy Limited · 23/038/TPP
1.8Application Withdrawn2024-01-30
Hammer, Skelwick - Wind Turbine
Constantine Wind Energy · 23/153/PP · 6.3 mo to decide
0.5Awaiting Construction2023-12-01
Nitshill Wind Farm, Hundland Hill
Nisthill Wind Farm Limited · 22/320/TPPMAJ
26.4Application Submitted2022-09-07
Orkney�s Community Wind Farm Project - Qanterness
Orkney Islands Council · 20/037/TPPMAJ · 22.1 mo to decide
28.8Awaiting Construction2021-12-21
Orkney�s Community Wind Farm Project - Hoy
Orkney Islands Council · 20/313/TPPMAJ · 14.8 mo to decide
28.8Awaiting Construction2021-12-21
Hammars Hill Wind Farm Extension
Hammars Hill Energy · 20/112/TPP · 17.9 mo to decide
8.4Planning Permission Expired2021-09-30
Orkney�s Community Wind Farm Project - Faray
Orkney Islands Council · 21/240/TPPMAJ
28.8Application Submitted2021-06-25
Hesta Head Wind Farm
Hoolan Energy/ Hesta Head Wind Farm · 17/083/TPPMAJ · 25.4 mo to decide
20.4Awaiting Construction2019-04-18
Costa Head Wind Farm
Hoolan Energy · 16/580/TPPMAJ · 28.3 mo to decide
16.3Awaiting Construction2019-04-18
Evie Wind Energy Project
Private Developer · 09/045/PPF · 71.5 mo to decide
2.3Planning Permission Expired2015-01-12
Rysa Wind Energy Project
Orkney Renewable Energy · 13/072/TPP
2.7Application Withdrawn2014-04-30
New Holland
Windflow UK · 13/261/TPP · 3.3 mo to decide
1Operational2013-11-06
Skeabrae Wind Energy Project
Skeabrae Renewables Ltd · 12/599/TPP
1.5Application Withdrawn2013-09-03
Bu Wind Farm Repowering
Scottish and Southern Energy (SSE) · 12/725/TPP · 5.2 mo to decide
2.6Abandoned2013-04-12
Work Farm Wind Turbines
S & JD Robertson Group Ltd · 12/699/TPP · 3.6 mo to decide
1.8Revised2013-01-31
Akla
Orkney Sustainable Energy · 10/631/PP · 24.3 mo to decide
2.7Awaiting Construction2012-12-17
Spurness Wind Farm Repowering
Scottish and Southern Energy (SSE) · 11/102/TPP · 4.6 mo to decide
10Operational2011-07-21
Barns of Ayre Wind Turbines (2)
Ayre Energy/Aquatera Ltd · 10/594/PP · 4 mo to decide
1.8Operational2011-03-12
Gallowhill
Private Developer · 08/491/PPF · 4.6 mo to decide
1.8Operational2009-03-02
Hammar's Hill
Hammers Hill Energy Ltd · 08/138/PPF · 9.9 mo to decide
4.3Operational2009-01-06
Burgar Hill (land Near), Evie
Unknown · 07/422/PPF · 16.9 mo to decide
2.3Operational2008-12-04
West Hill, Flotta
Scotrenewables (Scotland) Ltd · 04/224/PPF · 43.7 mo to decide
2Operational2007-12-18
Enyas Hill
Hainsford Energy · 04/16/350/PPS · 6.2 mo to decide
6Application Refused2005-01-05
Gruf Hill
Orkney Sustainable Energy · 02/410/PPF · 4.4 mo to decide
7.5Application Refused2003-03-01
Spurness Wind Farm
Scottish and Southern Energy (SSE) · 4 mo to decide
11Decommissioned2003-01-01
Flotta
Scotwind (Scottish Renewables) · 02/241/PPF · 3.1 mo to decide
1.8Operational2002-09-01
Rothiesholm
Longearth Ltd / Farm Energy · 01/006/PPF · 3.9 mo to decide
2.7Operational2001-05-01
Thorfinn Wind Farm - NM1500
Vestas · 02/020/PPF · 13 mo to decide
1.5Operational1999-11-22
Thorfinn Wind Farm - NM2000
Vestas · 02/189/PPF · 13 mo to decide
2.3Operational1999-11-22
Burgar Hill
Orkney Sustainable Energy · 4.7 mo to decide
5Operational1997-07-07
Bu Farm
Longearth Ltd/ Farm Energy
2.7Operational

Does Orkney Islands approve onshore wind schemes?

Yes — of the 28 onshore wind schemes Orkney Islands has decided, 93% were approved (26 granted, 2 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Orkney Islands?

The median time from application to decision is 6.2 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Orkney Islands consented?

159 MW has been consented across 26 approved schemes, with 14 MW refused. A further 5 applications awaits a decision.

Other technologies in Orkney Islands

Solar in Orkney IslandsBattery storage in Orkney Islands

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.