Renewable sites › Granville Ecopark
Granville Ecopark
Granville Ecopark is operational in Mid Ulster with a recorded capacity of 3 MW, and has been generating since 2014-06-10.
Planning and build timeline
| Application submitted | 2009-03-25 |
| Permission granted | 2010-02-02 10 months after submission |
| Operational | 2014-06-10 52 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Dungannon Energy Storage System Battery · Under Construction | 50 | 9.2 km |
Eshmore Wind Onshore · Operational | 6.9 | 10.8 km |
Crockagarron Ext Wind Onshore · Operational | 2.5 | 14.4 km |
Gortfinbar Wind Onshore · Operational | 15 | 14.7 km |
Crockagarran Wind Onshore · Operational | 15 | 14.8 km |
How big is Granville Ecopark?
Granville Ecopark has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Granville Ecopark?
REPD records the operator as Granville Ecopark. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Granville Ecopark approved and built?
The application was submitted on 2009-03-25. Permission was granted on 2010-02-02, 10 months later. The site became operational on 2014-06-10, 52 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 301.
Novarly Parcel · official public data, read properly · parcel.novarly.com