Renewable sites › Glenurquhart and Strathglass Wind Farm project
Glenurquhart and Strathglass Wind Farm project
Glenurquhart and Strathglass Wind Farm project is an operational 10 MW onshore wind farm in Highland, generating since 19 April 2013. Planning permission was granted on 18 November 2010, 6 months after submission. Operator of record: Corrimony Energy Ltd & Soirbheas.
Planning and build timeline
| Application submitted | 12 May 2010 |
| Permission granted | 18 November 2010 6 months after submission |
| Operational | 19 April 2013 29 months after consent |
Screening a site of your own?
Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Glenurquhart and Strathglass Wind Farm project’s recorded coordinate — swap in your own postcode or coordinates.
Highland’s record on onshore wind
Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Large Hydro · Operational | 7.5 | 6 km |
Large Hydro · Operational | 36 | 8.8 km |
Large Hydro · Operational | 15 | 9.1 km |
Wind Onshore · Operational | 110 | 12.2 km |
Small Hydro · Operational | 2.4 | 13.4 km |
How big is Glenurquhart and Strathglass Wind Farm project?
Glenurquhart and Strathglass Wind Farm project has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Glenurquhart and Strathglass Wind Farm project?
REPD records the operator as Corrimony Energy Ltd & Soirbheas. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Glenurquhart and Strathglass Wind Farm project approved and built?
The application was submitted on 12 May 2010. Permission was granted on 18 November 2010, 6 months later. The site became operational on 19 April 2013, 29 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3746.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode