Renewable sites › Glenurquhart and Strathglass Wind Farm project
Glenurquhart and Strathglass Wind Farm project
Glenurquhart and Strathglass Wind Farm project is operational in Highland with a recorded capacity of 10 MW, and has been generating since 2013-04-19.
Planning and build timeline
| Application submitted | 2010-05-12 |
| Permission granted | 2010-11-18 6 months after submission |
| Operational | 2013-04-19 29 months after consent |
Highland’s record on onshore wind
Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Fasnakyle Hydro Extension Large Hydro · Operational | 7.5 | 6 km |
Great Glen Scheme Large Hydro · Operational | 36 | 8.8 km |
Livishie Large Hydro · Operational | 15 | 9.1 km |
Bhlaraidh (previously Balmacaan) Wind Onshore · Operational | 110 | 12.2 km |
Mullardoch Tunnel Small Hydro · Operational | 2.4 | 13.4 km |
How big is Glenurquhart and Strathglass Wind Farm project?
Glenurquhart and Strathglass Wind Farm project has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Glenurquhart and Strathglass Wind Farm project?
REPD records the operator as Corrimony Energy Ltd & Soirbheas. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Glenurquhart and Strathglass Wind Farm project approved and built?
The application was submitted on 2010-05-12. Permission was granted on 2010-11-18, 6 months later. The site became operational on 2013-04-19, 29 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3746.