Renewable sitesFasnakyle Hydro Extension

Fasnakyle Hydro Extension

Fasnakyle Hydro Extension is an operational 7.5 MW hydro scheme in Highland, generating since 1 August 2006. Planning permission was granted on 1 April 2004, 7 months after submission. Operator of record: Scottish and Southern Energy (SSE).

7.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 August 2006
Large Hydro
Technology
Scottish and Southern Energy (SSE)
Highland
Authority
Scotland

Planning and build timeline

Application submitted4 September 2003
Permission granted1 April 2004
7 months after submission
Operational1 August 2006
28 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Highland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Fasnakyle Hydro Extension’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
106 km
Small Hydro · Operational
2.49.1 km
Large Hydro · Operational
3614.7 km
Large Hydro · Operational
1514.9 km

How big is Fasnakyle Hydro Extension?

Fasnakyle Hydro Extension has a recorded installed capacity of 7.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Fasnakyle Hydro Extension?

REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Fasnakyle Hydro Extension approved and built?

The application was submitted on 4 September 2003. Permission was granted on 1 April 2004, 7 months later. The site became operational on 1 August 2006, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 390.

Novarly Parcel · official public data, read properly · parcel.novarly.com