Renewable sites › Fasnakyle Hydro Extension
Fasnakyle Hydro Extension
Fasnakyle Hydro Extension is operational in Highland with a recorded capacity of 7.5 MW, and has been generating since 2006-08-01.
Planning and build timeline
| Application submitted | 2003-09-04 |
| Permission granted | 2004-04-01 7 months after submission |
| Operational | 2006-08-01 28 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Glenurquhart and Strathglass Wind Farm project Wind Onshore · Operational | 10 | 6 km |
Mullardoch Tunnel Small Hydro · Operational | 2.4 | 9.1 km |
Great Glen Scheme Large Hydro · Operational | 36 | 14.7 km |
Livishie Large Hydro · Operational | 15 | 14.9 km |
How big is Fasnakyle Hydro Extension?
Fasnakyle Hydro Extension has a recorded installed capacity of 7.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Fasnakyle Hydro Extension?
REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Fasnakyle Hydro Extension approved and built?
The application was submitted on 2003-09-04. Permission was granted on 2004-04-01, 7 months later. The site became operational on 2006-08-01, 28 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 390.