Novarly ParcelRenewable sites

Renewable sitesEnviRecover

EnviRecover

EnviRecover is operational in Wychavon with a recorded capacity of 15.5 MW, and has been generating since 2017-03-16.

15.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-16
EfW Incineration
Technology
Mercia Waste Management
Wychavon
Authority
England

Planning and build timeline

Application submitted2010-05-04
Permission granted2012-07-20
27 months after submission
Operational2017-03-16
56 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Waresley Landfill Site
Landfill Gas · Operational
1.60.9 km
Bumble Hole Lane, Dodford - Solar PV
Solar Photovoltaics · Operational
0.6710.1 km
Sandy Lane Generation Plant
Landfill Gas · Operational
211.5 km
Henwick Grove - Solar Panels
Solar Photovoltaics · Operational
14.5 km

How big is EnviRecover?

EnviRecover has a recorded installed capacity of 15.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates EnviRecover?

REPD records the operator as Mercia Waste Management. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was EnviRecover approved and built?

The application was submitted on 2010-05-04. Permission was granted on 2012-07-20, 27 months later. The site became operational on 2017-03-16, 56 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1005.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council