Renewable sites › Danes Moss Landfill Site (Extension)
Danes Moss Landfill Site (Extension)
Danes Moss Landfill Site (Extension) is an operational 2 MW landfill gas site in Cheshire East, generating since 16 June 2003. Planning permission was granted on 13 January 2003, 4 months after submission. Operator of record: Waste Recycling Group / NOVERA / Amber.
Planning and build timeline
| Application submitted | 20 September 2002 |
| Permission granted | 13 January 2003 4 months after submission |
| Operational | 16 June 2003 5 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Cheshire East: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Danes Moss Landfill Site (Extension)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Green Belt — Cheshire East
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 1.6 | 0 km |
Solar Photovoltaics · Under Construction | 2.5 | 14 km |
Solar Photovoltaics · Under Construction | 0.96 | 14.7 km |
How big is Danes Moss Landfill Site (Extension)?
Danes Moss Landfill Site (Extension) has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Danes Moss Landfill Site (Extension)?
REPD records the operator as Waste Recycling Group / NOVERA / Amber. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Danes Moss Landfill Site (Extension) approved and built?
The application was submitted on 20 September 2002. Permission was granted on 13 January 2003, 4 months later. The site became operational on 16 June 2003, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 641.