Novarly ParcelRenewable sites

Renewable sitesClaypit Moor Solar Farm (Lexham)

Claypit Moor Solar Farm (Lexham)

Claypit Moor Solar Farm (Lexham) is an operational 7.9 MW solar farm in Breckland, generating since 29 March 2013. Planning permission was granted on 21 December 2012, 3 months after submission. Operator of record: Lightsource Renewable Energy.

7.9 MW
Capacity
as recorded in REPD
Operational
Status
since 29 March 2013
Solar Photovoltaics
Technology
Lightsource Renewable Energy
Breckland
Authority
England

Planning and build timeline

Application submitted25 September 2012
Permission granted21 December 2012
3 months after submission
Operational29 March 2013
3 months after consent

Screening a site of your own?

RedlineUK · £39

Breckland approves 93% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Claypit Moor Solar Farm (Lexham)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Breckland’s record on solar

Breckland has decided 27 solar farms and approved 93%, taking a median of 2.7 months. See every solar farm decision in Breckland

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
49.95.5 km
Landfill Gas · Operational
110.2 km
Wind Onshore · Operational
1.811 km
Wind Onshore · Operational
1.511.6 km
Solar Photovoltaics · Operational
4.412.4 km
Solar Photovoltaics · Operational
11.512.8 km
Solar Photovoltaics · Operational
2613 km
Wind Onshore · Operational
14.413.2 km

How big is Claypit Moor Solar Farm (Lexham)?

Claypit Moor Solar Farm (Lexham) has a recorded installed capacity of 7.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Claypit Moor Solar Farm (Lexham)?

REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Claypit Moor Solar Farm (Lexham) approved and built?

The application was submitted on 25 September 2012. Permission was granted on 21 December 2012, 3 months later. The site became operational on 29 March 2013, 3 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1714.