Novarly ParcelRenewable sites

Renewable sitesChaorach Hydro

Chaorach Hydro

Chaorach Hydro is an operational 2 MW hydro scheme in Scotland, generating since 15 October 2016. Planning permission was granted on 4 December 2008, 20 months after submission. Operator of record: Green Highland Renewables.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 15 October 2016
Small Hydro
Technology
Green Highland Renewables
National
Authority
Scotland

Planning and build timeline

Application submitted2 April 2007
Permission granted4 December 2008
20 months after submission
Operational15 October 2016
94 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Chaorach Hydro’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Biomass (dedicated) · Operational
5.611.7 km
Small Hydro · Operational
2.113.8 km

How big is Chaorach Hydro?

Chaorach Hydro has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Chaorach Hydro?

REPD records the operator as Green Highland Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Chaorach Hydro approved and built?

The application was submitted on 2 April 2007. Permission was granted on 4 December 2008, 20 months later. The site became operational on 15 October 2016, 94 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 492.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode