Renewable sites › Brechfa Forest West
Brechfa Forest West
Brechfa Forest West is an operational 57.4 MW onshore wind farm in Wales, generating since 18 January 2018. Planning permission was granted on 12 March 2013, 16 months after submission. Operator of record: RWE Npower Renewables.
Planning and build timeline
| Application submitted | 4 November 2011 |
| Permission granted | 12 March 2013 16 months after submission |
| Operational | 18 January 2018 58 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Brechfa Forest West’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 23 | 8.1 km |
How big is Brechfa Forest West?
Brechfa Forest West has a recorded installed capacity of 57.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Brechfa Forest West?
REPD records the operator as RWE Npower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Brechfa Forest West approved and built?
The application was submitted on 4 November 2011. Permission was granted on 12 March 2013, 16 months later. The site became operational on 18 January 2018, 58 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3695.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode