Novarly ParcelRenewable sites

Renewable sitesBrechfa Forest West

Brechfa Forest West

Brechfa Forest West is operational in Wales with a recorded capacity of 57.4 MW, and has been generating since 2018-01-18.

57.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-01-18
Wind Onshore
Technology
RWE Npower Renewables
National
Authority
Wales

Planning and build timeline

Application submitted2011-11-04
Permission granted2013-03-12
16 months after submission
Operational2018-01-18
58 months after consent

Other built sites within 15 km

SiteMWDistance
Blaengwen
Wind Onshore · Operational
238.1 km

How big is Brechfa Forest West?

Brechfa Forest West has a recorded installed capacity of 57.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Brechfa Forest West?

REPD records the operator as RWE Npower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Brechfa Forest West approved and built?

The application was submitted on 2011-11-04. Permission was granted on 2013-03-12, 16 months later. The site became operational on 2018-01-18, 58 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3695.

Novarly Parcel · official public data, read properly · parcel.novarly.com