Renewable sites › Barmoor South Wind Farm
Barmoor South Wind Farm
Barmoor South Wind Farm is operational in Northumberland with a recorded capacity of 13.8 MW, and has been generating since 2015-01-19.
Planning and build timeline
| Application submitted | 2007-11-22 |
| Permission granted | 2010-01-21 26 months after submission |
| Operational | 2015-01-19 60 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Northumberland’s record on onshore wind
Northumberland has decided 31 onshore wind schemes and approved 52%, taking a median of 16.3 months. See every onshore wind scheme decision in Northumberland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Simpsons Malt Limited Biomass Biomass (dedicated) · Under Construction | 16 | 13.7 km |
How big is Barmoor South Wind Farm?
Barmoor South Wind Farm has a recorded installed capacity of 13.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Barmoor South Wind Farm?
REPD records the operator as EDF. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Barmoor South Wind Farm approved and built?
The application was submitted on 2007-11-22. Permission was granted on 2010-01-21, 26 months later. The site became operational on 2015-01-19, 60 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4163.
Novarly Parcel · official public data, read properly · parcel.novarly.com