Renewable sites › Bambers II
Bambers II
Bambers II is operational in East Lindsey with a recorded capacity of 4.6 MW, and has been generating since 2006-11-01.
Planning and build timeline
| Application submitted | 2005-05-04 |
| Permission granted | 2005-09-08 4 months after submission |
| Operational | 2006-11-01 14 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Lindsey’s record on onshore wind
East Lindsey has decided 14 onshore wind schemes and approved 50%, taking a median of 15.9 months. See every onshore wind scheme decision in East Lindsey →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bambers Farm Wind Onshore · Operational | 9.6 | 0 km |
Gayton Le Marsh Wind Farm Wind Onshore · Operational | 16.4 | 6.7 km |
High Leas Solar Photovoltaics · Operational | 6.5 | 9.6 km |
How big is Bambers II?
Bambers II has a recorded installed capacity of 4.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bambers II?
REPD records the operator as Ecotricity Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bambers II approved and built?
The application was submitted on 2005-05-04. Permission was granted on 2005-09-08, 4 months later. The site became operational on 2006-11-01, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2715.
Novarly Parcel · official public data, read properly · parcel.novarly.com