Auchencarroch Landfill

Auchencarroch Landfill is an operational 2.1 MW landfill gas site in West Dunbartonshire, generating since 15 August 2002. Planning permission was granted on 10 May 2001, 6 months after submission. Operator of record: Auchencarroch Energy Ltd / CLP.

2.1 MW
Capacity
as recorded in REPD
Operational
Status
since 15 August 2002
Landfill Gas
Technology
Auchencarroch Energy Ltd / CLP
West Dunbartonshire
Authority
Scotland

Planning and build timeline

Application submitted20 November 2000
Permission granted10 May 2001
6 months after submission
Operational15 August 2002
15 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in West Dunbartonshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Auchencarroch Landfill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
20.1 km
Solar Photovoltaics · Under Construction
0.182.7 km
Solar Photovoltaics · Operational
0.7515 km

How big is Auchencarroch Landfill?

Auchencarroch Landfill has a recorded installed capacity of 2.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Auchencarroch Landfill?

REPD records the operator as Auchencarroch Energy Ltd / CLP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Auchencarroch Landfill approved and built?

The application was submitted on 20 November 2000. Permission was granted on 10 May 2001, 6 months later. The site became operational on 15 August 2002, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 688.