Renewable planning › Solar › Scottish Government (S36)
Solar planning in Scottish Government (S36)
Scottish Government (S36) has decided 16 solar farms and approved 88% of them, taking a median of 16.2 months to decide. Consented capacity: 693 MW. 16 applications still awaiting a decision.
How Scottish Government (S36) compares
Against the 298 UK authorities with 5+ solar decisions, Scottish Government (S36) sits in the 21st percentile for approval rate (5 points below the England average) and the 1st percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (33)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Crystal Rig Solar Farm Fred Olsen Renewables · ECU00004759 · 12.9 mo to decide | 27.5 | Awaiting Construction | 2025-07-30 |
Kintore - Solar Photovoltaic Array Mespil Solar Energy · ECU00005245 | 50 | Application Submitted | 2025-07-29 |
Fernishaw Solar Farm & Battery Energy Storage Facility Elgin Energy (EEB67) · ECU00004871 · 19.1 mo to decide | 75 | Awaiting Construction | 2025-07-23 |
Stirches Renewable Energy Park - Solar Panels & Battery Energy Storage IB Vogt UK Limited · ECU00006015 | 30 | Application Submitted | 2025-07-03 |
Lower Bodachra - Solar Panels Novus Renewables Services Limited · ECU00004848 · 9.4 mo to decide | 72 | Awaiting Construction | 2025-06-24 |
Springfield - Solar Farm & Battery Energy Storage Voltalia UK Limited · ECU00004815 | 165 | Application Submitted | 2025-06-06 |
Bowshiel Farm - Solar Farm Voltalia UK · ECU00005085 | 165 | Application Submitted | 2025-06-06 |
Lairdmannoch Energy Park Wind2 / Octopus Energy · ECU00004900 | 20 | Application Submitted | 2025-05-27 |
Cossans Solar Farm - Solar Farm BLC Energy · ECU00005213 | 49.9 | Application Submitted | 2025-05-15 |
Hagshaw Energy Cluster � Western Expansion 3R Energy Solutions Limited · ECU00004623 | 60 | Application Submitted | 2025-05-08 |
Knockkippen Wind, Solar & Battery Farm Falck Renewables / REG Windpower · ECU00004523 · 34.2 mo to decide | 20 | Awaiting Construction | 2025-04-30 |
West Springfield Solar Farm - Solar Panels & BESS BLC Energy · ECU00006134 | 49.9 | Application Submitted | 2025-04-02 |
Tealing Solar Energy Park - Phase 2 Sirius EcoDev Limited · ECU00004882 · 16.2 mo to decide | 110 | Awaiting Construction | 2025-03-25 |
Mains Of Keithick Farm, Keithick - Battery Storage & Solar Farm EcoDev Group Limited · ECU00004521 · 31.7 mo to decide | 20.5 | Awaiting Construction | 2025-03-13 |
Earraghail Renewable Energy Development ScottishPower Renewables · ECU00003421 · 35.8 mo to decide | 5 | Application Refused | 2025-02-14 |
Allt an Tuir Renewable Energy Park REG Windpower Limited / ESB Energy Limited · ECU00005008 | 18 | Application Submitted | 2025-02-06 |
Rogerhill Solar and Battery Energy Storage System Green Switch Capital Limited · P/25/0018 | 100 | Application Submitted | 2025-01-15 |
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storage Scottish Power Renewables · ECU00002198 · 44.8 mo to decide | 40 | Awaiting Construction | 2025-01-09 |
Nettly Burn Renewable Energy Park Grupotec Solar UK 4 Ltd · ECU00006007 | 80 | Application Submitted | 2024-10-22 |
Loch Fergus Farm - Solar Farm Locogen · ECU00004855 · 15.7 mo to decide | 40 | Under Construction | 2024-10-22 |
M74 West Renewable Energy Park Renewco Power · ECU00005019 | 82.5 | Application Submitted | 2024-09-24 |
Hollandmey Renewable Energy Development Scottishpower Renewables · ECU00003353 · 33.9 mo to decide | 15 | Awaiting Construction | 2024-09-16 |
Stirling Battery and Solar Energy Park EcoDev Group Limited · ECU00005014 | 60 | Application Submitted | 2024-05-16 |
Lees Hill Energy Park Fred Olsen Renewables Limited · ECU00004571 | 60 | Application Submitted | 2024-04-16 |
Houston Solar PV Farm & Energy Storage Facility The Old Rectory · ECU00004825 | 75 | Application Submitted | 2023-10-04 |
Benthead Farm - Solar Farm & Battery Storage Locogen Limited · ECU00004702 · 8 mo to decide | 63 | Awaiting Construction | 2023-08-11 |
Frodo Solar and Battery Energy Development Green Energy International · ECU00003345 · 14 mo to decide | 60.1 | Awaiting Construction | 2023-05-16 |
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facility Elgin Energy Es Co Limited · ECU00003226 · 22.3 mo to decide | 50 | Awaiting Construction | 2022-12-22 |
Wemyss Estate - Randolph Solar Farm & Battery Energy Storage Elgin Energy · ECU00002222 · 14.5 mo to decide | 50 | Awaiting Construction | 2022-05-24 |
Teviot Wind Farm Muirhall Energy Limited · ECU00003249 | 34 | Application Submitted | 2022-05-20 |
Kilgallioch Windfarm (Extension - Solar) Scottish Power Renewables · ECU00001996 | 20 | Abandoned | 2019-12-16 |
Sheirdrim Renewable Energy Development - Solar ScottishPower Renewables · ECU00001957 | 20 | Appeal Refused | 2019-10-10 |
Milltown Airfield (Speyslaw) Elgin Energy · ECU00000452 · 10 mo to decide | 50 | Awaiting Construction | 2018-05-25 |
Does Scottish Government (S36) approve solar farms?
Yes — of the 16 solar farms Scottish Government (S36) has decided, 88% were approved (14 granted, 2 refused). The UK-wide rate for solar is 93%.
How long does a solar farm application take in Scottish Government (S36)?
The median time from application to decision is 16.2 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has Scottish Government (S36) consented?
693 MW has been consented across 14 approved schemes, with 25 MW refused. A further 16 applications awaits a decision.
Other technologies in Scottish Government (S36)
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.