Solar planning in North Warwickshire
North Warwickshire has decided 23 solar farms and approved 96% of them, taking a median of 1.9 months to decide. Consented capacity: 199 MW. 1 application still awaiting a decision.
How North Warwickshire compares
Against the 298 UK authorities with 5+ solar decisions, North Warwickshire sits in the 47th percentile for approval rate (3 points above the England average) and the 62nd percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (24)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Tamworth Logistics Park, Dordon - Solar Panels Indurent Management Limited · PAP/2026/0042 | 0.49 | Application Submitted | 2026-01-23 |
Kingsbury High School, Tamworth Road -Solar Panels EEnergy Group plc · PAP/2025/0542 · 1.7 mo to decide | 0.23 | Awaiting Construction | 2026-01-16 |
Park House Farm, Meriden Road - Solar Farm Enviromena Asset Management UK Limited · PAP/2023/0071 · 33.5 mo to decide | 47.7 | Awaiting Construction | 2025-12-11 |
Expeditors, Coleshill - Solar Panels, Unit 17A Expeditors · PAP/2025/0337 · 0.9 mo to decide | 0.15 | Awaiting Construction | 2025-08-29 |
Camp Farm, Knowle Hill - Solar Farm Ampyr Solar Europe · PAP/2024/0586 · 7.4 mo to decide | 49.9 | Awaiting Construction | 2025-08-18 |
WHS Plastics, Water Orton Lane - Solar Panels WHS Plastics Limited · 2024/06773/PA · 1.7 mo to decide | 1.08 | Awaiting Construction | 2024-12-19 |
BAC Jaguar Land Rover Battery Assembly Centre, Canton Lane - Solar Panels Columbia Threadneedle Investments Limited · PAP/2024/0034 · 1.2 mo to decide | 2.2 | Awaiting Construction | 2024-03-04 |
Coleshill Food Waste, Ad Plantmarconi Way - Solar Panels Severn Trent Green Power Group Limited · PAP/2023/0569 · 1.2 mo to decide | 0.18 | Awaiting Construction | 2024-01-29 |
Hams Hall National Distribution Park, Faraday Avenue - Solar Panels Columbia Threadneedle Investments Limited · PAP/2023/0540 · 1.5 mo to decide | 0.3 | Awaiting Construction | 2024-01-19 |
Euro Car Parts - Solar Panels & Battery Storage Ivegate Limited · PAP/2023/0325 · 1.4 mo to decide | 3 | Awaiting Construction | 2023-10-19 |
Bristan, Pooley Hall Drive - Solar Pv Panels Bristan Group Limited · PAP/2023/0359 · 1.4 mo to decide | 0.67 | Awaiting Construction | 2023-10-05 |
Highway Point, Gorsey Lane - Solar Panels Logicor · PAP/2023/0203 · 2.6 mo to decide | 0.61 | Awaiting Construction | 2023-09-28 |
Business Park, Meridian Drive - Solar Panels Maersk · PAP/2023/0316 · 1.8 mo to decide | 1.5 | Awaiting Construction | 2023-09-11 |
Copes Rough Wood, Lower House Lane - Solar Farm Fields Form Solar Limited · PAP/2022/0374 · 11.7 mo to decide | 5 | Awaiting Construction | 2023-09-08 |
Vauls Farm, Astley Lane - Solar Farm Industria Solar Bedworth Limited · PAP/2022/0544 · 8.8 mo to decide | 16 | Awaiting Construction | 2023-07-19 |
Cembre Limited Dunton Park, Kingsbury Road Cembre Limited · PAP/2023/0077 · 1.8 mo to decide | 0.94 | Awaiting Construction | 2023-04-24 |
Melbicks Garden Centre, Chester Road - Solar Panels Blue Diamond Limited · PAP/2022/0450 · 1.9 mo to decide | 0.38 | Awaiting Construction | 2022-11-03 |
Park Lane, Astley - Solar PV Farm Tor Energy Solar Limited · PAP/2021/0651 · 7.9 mo to decide | 30 | Awaiting Construction | 2022-07-28 |
Corley Smorral Lane - Photovoltaic Solar Arrays Barrs Family Enterprises Limited · PAP/2021/0605 · 8.2 mo to decide | 16.5 | Awaiting Construction | 2022-07-27 |
Meridian Drive, Dordon - Solar PV System Marshall Fleet Solutions · PAP/2022/0095 · 1.8 mo to decide | 0.16 | Awaiting Construction | 2022-05-05 |
Coton Road - Solar Photovoltaic Panels Food and Rural Affairs · PAP/2021/0562 · 5.1 mo to decide | 3 | Awaiting Construction | 2022-03-09 |
Land South of Pogmore Spinney Murex Energy · PAP/2015/0459 · 7.2 mo to decide | 5 | Operational | 2016-02-29 |
Lower House Lane Blue Planet Solar · PAP/2015/0614 · 2.3 mo to decide | 4 | Application Refused | 2015-12-15 |
Atherstone Foresight Solar Fund · PAP/2014/0483 · 2.1 mo to decide | 14.7 | Operational | 2014-11-14 |
Does North Warwickshire approve solar farms?
Yes — of the 23 solar farms North Warwickshire has decided, 96% were approved (22 granted, 1 refused). The UK-wide rate for solar is 93%.
How long does a solar farm application take in North Warwickshire?
The median time from application to decision is 1.9 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has North Warwickshire consented?
199 MW has been consented across 22 approved schemes, with 4 MW refused. A further 1 application awaits a decision.
Other technologies in North Warwickshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.