Renewable planning › Onshore wind › North Warwickshire
Onshore wind planning in North Warwickshire
North Warwickshire has decided 1 onshore wind scheme and approved 0% of them, taking a median of 6.2 months to decide.
⚠️ Small caseload (1 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How North Warwickshire compares
Against the 75 UK authorities with 5+ onshore wind decisions, North Warwickshire sits in the 0th percentile for approval rate (68 points below the England average) and the 91st percentile for speed.
Every recorded scheme (1)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Wienerberger Brick Works Wienberger Ltd · PAP/2013/0321 · 6.2 mo to decide | 2.5 | Appeal Refused | 2014-01-14 |
Does North Warwickshire approve onshore wind schemes?
Yes — of the 1 onshore wind schemes North Warwickshire has decided, 0% were approved (0 granted, 1 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a onshore wind scheme application take in North Warwickshire?
The median time from application to decision is 6.2 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has North Warwickshire consented?
0 MW has been consented across 0 approved schemes, with 3 MW refused. There are no applications currently awaiting a decision.
Other technologies in North Warwickshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.