Renewable planning › Battery storage › Mid Devon
Battery storage planning in Mid Devon
Mid Devon has decided 4 battery storage schemes and approved 100% of them, taking a median of 8 months to decide. Consented capacity: 436 MW. 3 applications still awaiting a decision.
⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Mid Devon compares
Against the 137 UK authorities with 5+ battery storage decisions, Mid Devon sits in the 73rd percentile for approval rate (8 points above the England average) and the 25th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (7)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Broad Path - Battery Storage Valencia Energy Limited · DCC/4419/2024 | — | Application Submitted | 2025-01-13 |
Hunters Way, Culmstock - Energy Storage Facility AMP Clean Energy · 24/00934/FULL� | 0.2 | Application Submitted | 2024-08-06 |
Junction 27, Westleigh - Battery Storage Clearstone Energy · 23/01351/MFUL · 7 mo to decide | 400 | Awaiting Construction | 2024-04-12 |
George Hil, Avranches Avenue - Micro Energy Storage Facility Aggregated Micro Power Holdings Plc · 23/01923/FULL · 2 mo to decide | 0.2 | Awaiting Construction | 2024-02-15 |
Petroc, Bolham Road - Battery Storage & Air Source Heat Pumps Petroc · 24/00192/FULL · 9.1 mo to decide | 1 | Awaiting Construction | 2024-01-29 |
Petroc College, Bolham Road - Solar, Battery & Ground Source Heat Pump Petroc · 23/00728/CLP | — | Revised | 2023-04-27 |
Langford Solar Farm JBM Solar Projects · 19/01679/MFUL · 48.2 mo to decide | 35 | Operational | 2022-12-05 |
Does Mid Devon approve battery storage schemes?
Yes — of the 4 battery storage schemes Mid Devon has decided, 100% were approved (4 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Mid Devon?
The median time from application to decision is 8 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Mid Devon consented?
436 MW has been consented across 4 approved schemes. A further 3 applications awaits a decision.
Other technologies in Mid Devon
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com