Renewable planning › Solar › Mid and East Antrim
Solar planning in Mid and East Antrim
Mid and East Antrim has decided 5 solar farms and approved 100% of them, taking a median of 5.2 months to decide. Consented capacity: 26 MW. 1 application still awaiting a decision.
⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Mid and East Antrim compares
Against the 298 UK authorities with 5+ solar decisions, Mid and East Antrim sits in the 77th percentile for approval rate (7 points above the England average) and the 6th percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (7)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Solar Farm Development in Ballymena Brooklands Altnagelvin No2 Limited · LA02/2024/0932/F · 3.8 mo to decide | 3.5 | Awaiting Construction | 2025-04-14 |
Solar Farm Development in Ballymena Brooklands Altnagelvin No2 Limited · LA02/2024/0707/PAN | — | Application Submitted | 2024-09-23 |
Solar PV Development in Ballymena HHT Management Limited · LA02/2024/0352/F · 3.8 mo to decide | 2.5 | Awaiting Construction | 2024-08-16 |
Solar PV Energy Development in Ballymena HHT Management Limited · LA02/2024/0353/F · 3.7 mo to decide | 2 | Awaiting Construction | 2024-08-14 |
Ballygarvey Road Elgin Energy EsCo · LA02/2015/0756/F · 8.6 mo to decide | 13 | Operational | 2016-09-08 |
Land at Dobbs Estate Lightsource Renewable Energy · V/2015/0038/F · 11.7 mo to decide | 21.8 | Abandoned | 2016-03-14 |
Red Brae Power Capital · LA02/2015/0017/F · 6.5 mo to decide | 5 | Planning Permission Expired | 2015-10-13 |
Does Mid and East Antrim approve solar farms?
Yes — of the 5 solar farms Mid and East Antrim has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for solar is 93%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a solar farm application take in Mid and East Antrim?
The median time from application to decision is 5.2 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has Mid and East Antrim consented?
26 MW has been consented across 5 approved schemes. A further 1 application awaits a decision.
Other technologies in Mid and East Antrim
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.