Renewable planning › Onshore wind › East Hertfordshire
Onshore wind planning in East Hertfordshire
East Hertfordshire has decided 2 onshore wind schemes and approved 0% of them, taking a median of 5.9 months to decide.
⚠️ Small caseload (2 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How East Hertfordshire compares
Against the 75 UK authorities with 5+ onshore wind decisions, East Hertfordshire sits in the 0th percentile for approval rate (68 points below the UK average) and the 91st percentile for speed.
Screening a site of your own?
East Hertfordshire approves 0% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Every recorded scheme (2)
| Scheme | MW | Status | Decided |
|---|---|---|---|
High Elms Lane Turbine R H Bott & Son Ltd · 3/11/1190/FP · 3.7 mo to decide | 2 | Application Refused | 2011-10-26 |
Benington Wind Farm R H Bott & Son Ltd · 3/08/0889/FP · 8 mo to decide | 6.8 | Application Refused | 2009-01-14 |
Does East Hertfordshire approve onshore wind schemes?
Yes — of the 2 onshore wind schemes East Hertfordshire has decided, 0% were approved (0 granted, 2 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a onshore wind scheme application take in East Hertfordshire?
The median time from application to decision is 5.9 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has East Hertfordshire consented?
0 MW has been consented across 0 approved schemes, with 9 MW refused. There are no applications currently awaiting a decision.
Other technologies in East Hertfordshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.