Renewable planning SolarCauseway Coast and Glens

Solar planning in Causeway Coast and Glens

Causeway Coast and Glens has decided 4 solar farms and approved 100% of them, taking a median of 7.1 months to decide. Consented capacity: 49 MW. 4 applications still awaiting a decision.

100%
Approved
4 granted · 0 refused
7.1 mo
Median decision
UK 2.3 mo
49 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Causeway Coast and Glens compares

Against the 298 UK authorities with 5+ solar decisions, Causeway Coast and Glens sits in the 77th percentile for approval rate (7 points above the England average) and the 2nd percentile for speed.

Decisions by year

35Approved — 1 (2015)115Approved — 1 (2016)116Approved — 1 (2024)124
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (8)

SchemeMWStatusDecided
Solar PV Energy Development in Ballycastle
HHT Renewables Limited · LA01/2024/0410/F · 6.4 mo to decide
Awaiting Construction2024-10-08
Power Generation Development in Coleraine
Private Developer · LA01/2021/1460/PAN
Application Submitted2021-11-25
Lidl Nutts Corner
Lidl Northern Ireland · LA01/2020/0527/F
0.2Application Submitted2020-06-03
Shinny Road Macosquin
Northern Farm Partnership · LA01/2020/0279/F
1Application Submitted2020-03-06
Bann Road (Tullaghans Road)
Greencoat Capital · LA01/2015/1045/F · 7.7 mo to decide
25Operational2016-08-04
Kells Solar Farm
Elgin Energy EsCo · LA01/2015/0980/F · 6.1 mo to decide
25Revised2016-05-31
Finvoy Road
Lightsource Renewable Energy · D/2014/0234/F · 8.2 mo to decide
5.9Operational2015-08-10
Bann Road (Rasharkin)
Elgin Energy · D/2014/0181/F
18Operational2014-09-19

Does Causeway Coast and Glens approve solar farms?

Yes — of the 4 solar farms Causeway Coast and Glens has decided, 100% were approved (4 granted, 0 refused). The UK-wide rate for solar is 93%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a solar farm application take in Causeway Coast and Glens?

The median time from application to decision is 7.1 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Causeway Coast and Glens consented?

49 MW has been consented across 4 approved schemes. A further 4 applications awaits a decision.

Other technologies in Causeway Coast and Glens

Battery storage in Causeway Coast and GlensOnshore wind in Causeway Coast and Glens

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.