Renewable planning › Battery storage › South Ayrshire
Battery storage planning in South Ayrshire
South Ayrshire has decided 1 battery storage scheme and approved 100% of them, taking a median of 3.4 months to decide. Consented capacity: 50 MW. 1 application still awaiting a decision.
⚠️ Small caseload (1 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How South Ayrshire compares
Against the 137 UK authorities with 5+ battery storage decisions, South Ayrshire sits in the 73rd percentile for approval rate (8 points above the England average) and the 81st percentile for speed.
Every recorded scheme (2)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Hillhouse Quarry, Railway Bridge - Battery Storage Hillhouse Quarry Company Limited · 24/00424/APP | 0.5 | Application Submitted | 2024-06-05 |
Holmston Road - Battery Storage Facility Field Energy · 22/00505/PAN · 3.4 mo to decide | 49.9 | Under Construction | 2023-06-30 |
Does South Ayrshire approve battery storage schemes?
Yes — of the 1 battery storage schemes South Ayrshire has decided, 100% were approved (1 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in South Ayrshire?
The median time from application to decision is 3.4 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has South Ayrshire consented?
50 MW has been consented across 1 approved scheme. A further 1 application awaits a decision.
Other technologies in South Ayrshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com
Screen a specific site here · All authorities · UK property report