Renewable planning › Battery storage › Boston
Battery storage planning in Boston
Boston has decided 4 battery storage schemes and approved 100% of them, taking a median of 4.7 months to decide. Consented capacity: 521 MW. 2 applications still awaiting a decision.
⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Boston compares
Against the 137 UK authorities with 5+ battery storage decisions, Boston sits in the 73rd percentile for approval rate (8 points above the England average) and the 65th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (6)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Boston West Business Park - Micro Energy Storage AMP Clean Energy · B/26/0105 | 0.2 | Application Submitted | 2026-02-27 |
Hammond Bicker Fen - Battery Energy Storage System Bicker Drove Limited · B/25/0224 | — | Application Submitted | 2025-05-28 |
Vicarage Drove - Battery Storage Facility Vicarage Drove Bess Limited (AGR Group) · B/24/0363 · 4.9 mo to decide | — | Awaiting Construction | 2025-02-05 |
Bicker Fen Bess, Vicarage Drove - Battery Storage FRV TH Powertek Limited · B/24/0415 · 3.9 mo to decide | 400 | Awaiting Construction | 2025-02-05 |
Bicker Drove - Battery Energy Storage System Net Zero Twenty Two Limited · B/24/0374 · 4.6 mo to decide | 100 | Awaiting Construction | 2025-02-05 |
Vicarage Drove - Solar farm & Battery storage Renewable Connections Developments Limited · B/21/0443 · 27.6 mo to decide | 20.5 | Awaiting Construction | 2024-01-23 |
Does Boston approve battery storage schemes?
Yes — of the 4 battery storage schemes Boston has decided, 100% were approved (4 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Boston?
The median time from application to decision is 4.7 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Boston consented?
521 MW has been consented across 4 approved schemes. A further 2 applications awaits a decision.
Other technologies in Boston
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.