Viking Wind Farm

Viking Wind Farm is an operational 443 MW onshore wind farm in Scotland, generating since 1 September 2024. Planning permission was granted on 24 May 2019, 6 months after submission. Operator of record: Viking Energy Wind Farm.

443 MW
Capacity
as recorded in REPD
Operational
Status
since 1 September 2024
Wind Onshore
Technology
Viking Energy Wind Farm
National
Authority
Scotland

Planning and build timeline

Application submitted14 November 2018
Permission granted24 May 2019
6 months after submission
Operational1 September 2024
63 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Viking Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

How big is Viking Wind Farm?

Viking Wind Farm has a recorded installed capacity of 443 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Viking Wind Farm?

REPD records the operator as Viking Energy Wind Farm. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Viking Wind Farm approved and built?

The application was submitted on 14 November 2018. Permission was granted on 24 May 2019, 6 months later. The site became operational on 1 September 2024, 63 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6828.