Renewable sites › Victoria Road - Solar Photovoltaic System
Victoria Road - Solar Photovoltaic System
Victoria Road - Solar Photovoltaic System is operational in South Norfolk with a recorded capacity of 0.7 MW, and has been generating since 2022-06-01.
Planning and build timeline
| Application submitted | 2022-03-14 |
| Permission granted | 2022-04-27 1 months after submission |
| Operational | 2022-06-01 1 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Norfolk’s record on solar
South Norfolk has decided 28 solar farms and approved 96%, taking a median of 4.2 months. See every solar farm decision in South Norfolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Humphrey Group Wind Onshore · Operational | 5 | 4.2 km |
Eye Biomass Plant Biomass (dedicated) · Operational | 14.3 | 4.5 km |
Kenninghall Solar / Hazeldick Solar Solar Photovoltaics · Operational | 8 | 10.5 km |
Attleborough Road Solar Farm Solar Photovoltaics · Under Construction | 30 | 14.9 km |
How big is Victoria Road - Solar Photovoltaic System?
Victoria Road - Solar Photovoltaic System has a recorded installed capacity of 0.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Victoria Road - Solar Photovoltaic System?
REPD records the operator as WM Morrisons Supermarkets Plc. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Victoria Road - Solar Photovoltaic System approved and built?
The application was submitted on 2022-03-14. Permission was granted on 2022-04-27, 1 months later. The site became operational on 2022-06-01, 1 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10868.
Novarly Parcel · official public data, read properly · parcel.novarly.com