Eye Biomass Plant is an operational 14.3 MW biomass plant in Mid Suffolk, generating since 1 July 1992. REPD does not record the planning grant date. Operator of record: South Western Power (NOVERA).
Planning and build timeline
| Application submitted | not recorded |
| Permission granted | not recorded |
| Operational | 1 July 1992 |
Screening a site of your own?
Redline runs the record on your own boundary in Mid Suffolk: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Eye Biomass Plant’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 5 | 0.4 km |
Solar Photovoltaics · Operational | 0.7 | 4.5 km |
Solar Photovoltaics · Operational | 8 | 14.5 km |
How big is Eye Biomass Plant?
Eye Biomass Plant has a recorded installed capacity of 14.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Eye Biomass Plant?
REPD records the operator as South Western Power (NOVERA). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Eye Biomass Plant approved and built?
REPD does not record a submission date. REPD does not record a grant date. The site became operational on 1 July 1992.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 82.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode