Novarly ParcelRenewable sites

Renewable sitesUisge Dubh Hydro

Uisge Dubh Hydro

Uisge Dubh Hydro is an operational 2 MW hydro scheme in Highland, generating since 7 December 2017. Planning permission was granted on 28 August 2013, 8 months after submission. Operator of record: Gilkes Energy.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 7 December 2017
Small Hydro
Technology
Gilkes Energy
Highland
Authority
Scotland

Planning and build timeline

Application submitted19 December 2012
Permission granted28 August 2013
8 months after submission
Operational7 December 2017
51 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Highland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Uisge Dubh Hydro’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Small Hydro · Operational
13.5 km
Small Hydro · Operational
1.47.9 km
Small Hydro · Operational
213.7 km

How big is Uisge Dubh Hydro?

Uisge Dubh Hydro has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Uisge Dubh Hydro?

REPD records the operator as Gilkes Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Uisge Dubh Hydro approved and built?

The application was submitted on 19 December 2012. Permission was granted on 28 August 2013, 8 months later. The site became operational on 7 December 2017, 51 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 444.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode