Renewable sites › River Taodail Hydro
River Taodail Hydro
River Taodail Hydro is an operational 1.4 MW hydro scheme in Highland, generating since 15 January 2017. Planning permission was granted on 15 July 2013, 7 months after submission. Operator of record: Gilkes Energy.
Planning and build timeline
| Application submitted | 19 December 2012 |
| Permission granted | 15 July 2013 7 months after submission |
| Operational | 15 January 2017 42 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Highland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with River Taodail Hydro’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Small Hydro · Operational | 1 | 7.4 km |
Small Hydro · Operational | 2 | 7.9 km |
Small Hydro · Operational | 2 | 12.3 km |
How big is River Taodail Hydro?
River Taodail Hydro has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates River Taodail Hydro?
REPD records the operator as Gilkes Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was River Taodail Hydro approved and built?
The application was submitted on 19 December 2012. Permission was granted on 15 July 2013, 7 months later. The site became operational on 15 January 2017, 42 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 448.