Novarly ParcelRenewable sites

Renewable sitesThree Maids Hill Solar Farm

Three Maids Hill Solar Farm

Three Maids Hill Solar Farm is operational in Winchester with a recorded capacity of 25 MW, and has been generating since 2023-01-01.

25 MW
Capacity
as recorded in REPD
Operational
Status
since 2023-01-01
Solar Photovoltaics
Technology
Environmenta Asset Management
Winchester
Authority
England

Planning and build timeline

Application submitted2020-10-21
Permission granted2021-05-19
7 months after submission
Operational2023-01-01
19 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Winchester’s record on solar

Winchester has decided 24 solar farms and approved 100%, taking a median of 2.9 months. See every solar farm decision in Winchester

Other built sites within 15 km

SiteMWDistance
Owls Lodge Farm
Solar Photovoltaics · Operational
58.1 km
Owls Lodge Farm Extension
Solar Photovoltaics · Operational
58.4 km
Winchester Battery Storage
Battery · Operational
198.6 km
Fullenton Solar Farm
Solar Photovoltaics · Operational
4.29.1 km
Field House Solar / Hursley Road
Solar Photovoltaics · Operational
6.412.1 km
Cowdown Lane
Solar Photovoltaics · Operational
4012.1 km
Westover Farm
Solar Photovoltaics · Operational
712.4 km
Abbots Ann
Solar Photovoltaics · Operational
712.8 km

How big is Three Maids Hill Solar Farm?

Three Maids Hill Solar Farm has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Three Maids Hill Solar Farm?

REPD records the operator as Environmenta Asset Management. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Three Maids Hill Solar Farm approved and built?

The application was submitted on 2020-10-21. Permission was granted on 2021-05-19, 7 months later. The site became operational on 2023-01-01, 19 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8011.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council