Renewable sites › Three Maids Hill Solar Farm
Three Maids Hill Solar Farm
Three Maids Hill Solar Farm is operational in Winchester with a recorded capacity of 25 MW, and has been generating since 2023-01-01.
Planning and build timeline
| Application submitted | 2020-10-21 |
| Permission granted | 2021-05-19 7 months after submission |
| Operational | 2023-01-01 19 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Nutrient-neutrality catchment — River Itchen SAC
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Winchester’s record on solar
Winchester has decided 24 solar farms and approved 100%, taking a median of 2.9 months. See every solar farm decision in Winchester →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Owls Lodge Farm Solar Photovoltaics · Operational | 5 | 8.1 km |
Owls Lodge Farm Extension Solar Photovoltaics · Operational | 5 | 8.4 km |
Winchester Battery Storage Battery · Operational | 19 | 8.6 km |
Fullenton Solar Farm Solar Photovoltaics · Operational | 4.2 | 9.1 km |
Field House Solar / Hursley Road Solar Photovoltaics · Operational | 6.4 | 12.1 km |
Cowdown Lane Solar Photovoltaics · Operational | 40 | 12.1 km |
Westover Farm Solar Photovoltaics · Operational | 7 | 12.4 km |
Abbots Ann Solar Photovoltaics · Operational | 7 | 12.8 km |
How big is Three Maids Hill Solar Farm?
Three Maids Hill Solar Farm has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Three Maids Hill Solar Farm?
REPD records the operator as Environmenta Asset Management. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Three Maids Hill Solar Farm approved and built?
The application was submitted on 2020-10-21. Permission was granted on 2021-05-19, 7 months later. The site became operational on 2023-01-01, 19 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8011.