Renewable sites › Rosehall Hill Forest Windfarm
Rosehall Hill Forest Windfarm
Rosehall Hill Forest Windfarm is an operational 24.7 MW onshore wind farm in Highland, generating since 28 February 2013. Planning permission was granted on 30 September 2006, 10 months after submission. Operator of record: E.ON UK.
Planning and build timeline
| Application submitted | 30 November 2005 |
| Permission granted | 30 September 2006 10 months after submission |
| Operational | 28 February 2013 77 months after consent |
Screening a site of your own?
Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Rosehall Hill Forest Windfarm’s recorded coordinate — swap in your own postcode or coordinates.
Highland’s record on onshore wind
Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 38 | 2.9 km |
Large Hydro · Operational | 10 | 3 km |
Small Hydro · Operational | 3.5 | 8.6 km |
Wind Onshore · Under Construction | 49.9 | 10.6 km |
Wind Onshore · Operational | 7.5 | 11.8 km |
How big is Rosehall Hill Forest Windfarm?
Rosehall Hill Forest Windfarm has a recorded installed capacity of 24.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rosehall Hill Forest Windfarm?
REPD records the operator as E.ON UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rosehall Hill Forest Windfarm approved and built?
The application was submitted on 30 November 2005. Permission was granted on 30 September 2006, 10 months later. The site became operational on 28 February 2013, 77 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4051.
Novarly Parcel · official public data, read properly · parcel.novarly.com