Pines Burn Wind Farm is an operational 33.6 MW onshore wind farm in Scottish Borders, generating since 1 October 2024. Planning permission was granted on 17 August 2018, 19 months after submission. Operator of record: EnergieKontor UK.

33.6 MW
Capacity
as recorded in REPD
Operational
Status
since 1 October 2024
Wind Onshore
Technology
EnergieKontor UK
Scottish Borders
Authority
Scotland

Planning and build timeline

Application submitted11 January 2017
Permission granted17 August 2018
19 months after submission
Operational1 October 2024
73 months after consent

Screening a site of your own?

RedlineUK · £39

Scottish Borders approves 56% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Pines Burn Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Borders’s record on onshore wind

Scottish Borders has decided 41 onshore wind schemes and approved 56%, taking a median of 13.6 months. See every onshore wind scheme decision in Scottish Borders

How big is Pines Burn Wind Farm?

Pines Burn Wind Farm has a recorded installed capacity of 33.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pines Burn Wind Farm?

REPD records the operator as EnergieKontor UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pines Burn Wind Farm approved and built?

The application was submitted on 11 January 2017. Permission was granted on 17 August 2018, 19 months later. The site became operational on 1 October 2024, 73 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6147.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode