Ora More
Ora More is an operational 15 MW onshore wind farm in Fermanagh and Omagh, generating since 30 March 2017. Planning permission was granted on 30 March 2011, 63 months after submission. Operator of record: Natural Power.
Planning and build timeline
| Application submitted | 15 December 2005 |
| Permission granted | 30 March 2011 63 months after submission |
| Operational | 30 March 2017 72 months after consent |
Screening a site of your own?
Fermanagh and Omagh approves 92% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Ora More’s recorded coordinate — swap in your own postcode or coordinates.
Fermanagh and Omagh’s record on onshore wind
Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92%, taking a median of 20.9 months. See every onshore wind scheme decision in Fermanagh and Omagh →
How big is Ora More?
Ora More has a recorded installed capacity of 15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ora More?
REPD records the operator as Natural Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ora More approved and built?
The application was submitted on 15 December 2005. Permission was granted on 30 March 2011, 63 months later. The site became operational on 30 March 2017, 72 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4654.