Renewable sites › New Holland
New Holland
New Holland is operational in Orkney Islands with a recorded capacity of 1 MW, and has been generating since 2014-10-20.
Planning and build timeline
| Application submitted | 2013-07-29 |
| Permission granted | 2013-11-06 3 months after submission |
| Operational | 2014-10-20 11 months after consent |
Orkney Islands’s record on onshore wind
Orkney Islands has decided 28 onshore wind schemes and approved 93%, taking a median of 6.2 months. See every onshore wind scheme decision in Orkney Islands →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Barns of Ayre Wind Turbines (2) Wind Onshore · Operational | 1.8 | 8.9 km |
Orkney Storage Park Project Battery · Operational | 2 | 9.6 km |
How big is New Holland?
New Holland has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates New Holland?
REPD records the operator as Windflow UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was New Holland approved and built?
The application was submitted on 2013-07-29. Permission was granted on 2013-11-06, 3 months later. The site became operational on 2014-10-20, 11 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3321.