Renewable sitesMonan Hill Wind Turbines

Monan Hill Wind Turbines

Monan Hill Wind Turbines is an operational 1.5 MW onshore wind farm in Na h-Eileanan Siar, generating since 19 March 2015. Planning permission was granted on 14 February 2008, 21 months after submission. Operator of record: North Harris Trust.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 19 March 2015
Wind Onshore
Technology
North Harris Trust
Na h-Eileanan Siar
Authority
Scotland

Planning and build timeline

Application submitted24 May 2006
Permission granted14 February 2008
21 months after submission
Operational19 March 2015
85 months after consent

Screening a site of your own?

RedlineUK · £39

Na h-Eileanan Siar approves 83% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Monan Hill Wind Turbines’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Na h-Eileanan Siar’s record on onshore wind

Na h-Eileanan Siar has decided 12 onshore wind schemes and approved 83%, taking a median of 18.9 months. See every onshore wind scheme decision in Na h-Eileanan Siar

How big is Monan Hill Wind Turbines?

Monan Hill Wind Turbines has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Monan Hill Wind Turbines?

REPD records the operator as North Harris Trust. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Monan Hill Wind Turbines approved and built?

The application was submitted on 24 May 2006. Permission was granted on 14 February 2008, 21 months later. The site became operational on 19 March 2015, 85 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4629.