Renewable sitesMoel Maelogen A Phase 2

Moel Maelogen A Phase 2

Moel Maelogen A Phase 2 is an operational 11.7 MW onshore wind farm in Conwy, generating since 1 October 2008. Planning permission was granted on 26 November 2004, 18 months after submission. Operator of record: John Laing Environmental Assets Group.

11.7 MW
Capacity
as recorded in REPD
Operational
Status
since 1 October 2008
Wind Onshore
Technology
John Laing Environmental Assets Group
Conwy
Authority
Wales

Planning and build timeline

Application submitted12 June 2003
Permission granted26 November 2004
18 months after submission
Operational1 October 2008
46 months after consent

Screening a site of your own?

RedlineUK · £39

Conwy approves 57% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Moel Maelogen A Phase 2’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Conwy’s record on onshore wind

Conwy has decided 7 onshore wind schemes and approved 57%, taking a median of 6.3 months. See every onshore wind scheme decision in Conwy

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
2.60 km
Large Hydro · Operational
3210 km

How big is Moel Maelogen A Phase 2?

Moel Maelogen A Phase 2 has a recorded installed capacity of 11.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Moel Maelogen A Phase 2?

REPD records the operator as John Laing Environmental Assets Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Moel Maelogen A Phase 2 approved and built?

The application was submitted on 12 June 2003. Permission was granted on 26 November 2004, 18 months later. The site became operational on 1 October 2008, 46 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3172.

Novarly Parcel · official public data, read properly · parcel.novarly.com