Renewable sites › Moel Maelogen A
Moel Maelogen A
Moel Maelogen A is operational in Conwy with a recorded capacity of 2.6 MW, and has been generating since 2003-01-30.
Planning and build timeline
| Application submitted | 1999-08-20 |
| Permission granted | 1999-12-15 4 months after submission |
| Operational | 2003-01-30 38 months after consent |
Conwy’s record on onshore wind
Conwy has decided 7 onshore wind schemes and approved 57%, taking a median of 6.3 months. See every onshore wind scheme decision in Conwy →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Moel Maelogen A Phase 2 Wind Onshore · Operational | 11.7 | 0 km |
Dolgarrog Large Hydro · Operational | 32 | 10 km |
How big is Moel Maelogen A?
Moel Maelogen A has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Moel Maelogen A?
REPD records the operator as John Laing Environmental Assets Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Moel Maelogen A approved and built?
The application was submitted on 1999-08-20. Permission was granted on 1999-12-15, 4 months later. The site became operational on 2003-01-30, 38 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2653.