Novarly ParcelRenewable sites

Renewable sitesMiddlemoor

Middlemoor

Middlemoor is operational in Northumberland with a recorded capacity of 54 MW, and has been generating since 2013-09-30.

54 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-09-30
Wind Onshore
Technology
Npower Renewables
Northumberland
Authority
England

Planning and build timeline

Application submitted2005-12-07
Permission granted2008-08-07
32 months after submission
Operational2013-09-30
62 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Northumberland’s record on onshore wind

Northumberland has decided 31 onshore wind schemes and approved 52%, taking a median of 16.3 months. See every onshore wind scheme decision in Northumberland

Other built sites within 15 km

SiteMWDistance
Wandylaw
Wind Onshore · Operational
20.52.3 km
Wooperton Station, Wooperton - Solar Farm
Solar Photovoltaics · Under Construction
5.5610.2 km

How big is Middlemoor?

Middlemoor has a recorded installed capacity of 54 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Middlemoor?

REPD records the operator as Npower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Middlemoor approved and built?

The application was submitted on 2005-12-07. Permission was granted on 2008-08-07, 32 months later. The site became operational on 2013-09-30, 62 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4019.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council