Renewable sites › Middlemoor
Middlemoor
Middlemoor is an operational 54 MW onshore wind farm in Northumberland, generating since 30 September 2013. Planning permission was granted on 7 August 2008, 32 months after submission. Operator of record: Npower Renewables.
Planning and build timeline
| Application submitted | 7 December 2005 |
| Permission granted | 7 August 2008 32 months after submission |
| Operational | 30 September 2013 62 months after consent |
Screening a site of your own?
Northumberland approves 52% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Middlemoor’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Northumberland’s record on onshore wind
Northumberland has decided 31 onshore wind schemes and approved 52%, taking a median of 16.3 months. See every onshore wind scheme decision in Northumberland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 20.5 | 2.3 km |
Solar Photovoltaics · Under Construction | 5.56 | 10.2 km |
How big is Middlemoor?
Middlemoor has a recorded installed capacity of 54 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Middlemoor?
REPD records the operator as Npower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Middlemoor approved and built?
The application was submitted on 7 December 2005. Permission was granted on 7 August 2008, 32 months later. The site became operational on 30 September 2013, 62 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4019.