Novarly ParcelRenewable sites

Renewable sitesLongpark

Longpark

Longpark is an operational 38 MW onshore wind farm in Scottish Borders, generating since 1 September 2009. Planning permission was granted on 31 August 2005, 18 months after submission. Operator of record: Wind Prospect.

38 MW
Capacity
as recorded in REPD
Operational
Status
since 1 September 2009
Wind Onshore
Technology
Wind Prospect
Scottish Borders
Authority
Scotland

Planning and build timeline

Application submitted16 February 2004
Permission granted31 August 2005
18 months after submission
Operational1 September 2009
48 months after consent

Screening a site of your own?

RedlineUK · £39

Scottish Borders approves 56% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Longpark’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Borders’s record on onshore wind

Scottish Borders has decided 41 onshore wind schemes and approved 56%, taking a median of 13.6 months. See every onshore wind scheme decision in Scottish Borders

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
27.611.5 km
Wind Onshore · Operational
29.813.1 km

How big is Longpark?

Longpark has a recorded installed capacity of 38 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Longpark?

REPD records the operator as Wind Prospect. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Longpark approved and built?

The application was submitted on 16 February 2004. Permission was granted on 31 August 2005, 18 months later. The site became operational on 1 September 2009, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3605.

Novarly Parcel · official public data, read properly · parcel.novarly.com