Renewable sitesLochcarnan Community Windfarm

Lochcarnan Community Windfarm

Lochcarnan Community Windfarm is an operational 6.9 MW onshore wind farm in Na h-Eileanan Siar, generating since 18 February 2013. Planning permission was granted on 21 December 2011, 37 months after submission. Operator of record: Storas Uibhist.

6.9 MW
Capacity
as recorded in REPD
Operational
Status
since 18 February 2013
Wind Onshore
Technology
Storas Uibhist
Na h-Eileanan Siar
Authority
Scotland

Planning and build timeline

Application submitted4 December 2008
Permission granted21 December 2011
37 months after submission
Operational18 February 2013
14 months after consent

Screening a site of your own?

RedlineUK · £39

Na h-Eileanan Siar approves 83% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Lochcarnan Community Windfarm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Na h-Eileanan Siar’s record on onshore wind

Na h-Eileanan Siar has decided 12 onshore wind schemes and approved 83%, taking a median of 18.9 months. See every onshore wind scheme decision in Na h-Eileanan Siar

How big is Lochcarnan Community Windfarm?

Lochcarnan Community Windfarm has a recorded installed capacity of 6.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lochcarnan Community Windfarm?

REPD records the operator as Storas Uibhist. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lochcarnan Community Windfarm approved and built?

The application was submitted on 4 December 2008. Permission was granted on 21 December 2011, 37 months later. The site became operational on 18 February 2013, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3670.