Llyn Brianne Dam is operational in Ceredigion with a recorded capacity of 4.4 MW, and has been generating since 1997-02-01.

4.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1997-02-01
Small Hydro
Technology
Dwr Cymru Welsh Water
Ceredigion
Authority
Wales

Planning and build timeline

Application submitted1994-02-08
Permission granted1994-05-27
4 months after submission
Operational1997-02-01
32 months after consent

Other built sites within 15 km

SiteMWDistance
Ystradffin Hydropower Project
Small Hydro · Under Construction
1.82.8 km

How big is Llyn Brianne Dam?

Llyn Brianne Dam has a recorded installed capacity of 4.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Llyn Brianne Dam?

REPD records the operator as Dwr Cymru Welsh Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Llyn Brianne Dam approved and built?

The application was submitted on 1994-02-08. Permission was granted on 1994-05-27, 4 months later. The site became operational on 1997-02-01, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 415.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council