Renewable sites › Llandulas Landfill Scheme
Llandulas Landfill Scheme
Llandulas Landfill Scheme is an operational 2.9 MW landfill gas site in Conwy, generating since 19 July 1999. Planning permission was granted on 19 March 1998, 4 months after submission. Operator of record: Waste Recycling Group.
Planning and build timeline
| Application submitted | 14 November 1997 |
| Permission granted | 19 March 1998 4 months after submission |
| Operational | 19 July 1999 16 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Conwy: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Llandulas Landfill Scheme’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 7.5 km |
Wind Offshore · Operational | 90 | 9.5 km |
Anaerobic Digestion · Operational | 1 | 14.4 km |
How big is Llandulas Landfill Scheme?
Llandulas Landfill Scheme has a recorded installed capacity of 2.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Llandulas Landfill Scheme?
REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Llandulas Landfill Scheme approved and built?
The application was submitted on 14 November 1997. Permission was granted on 19 March 1998, 4 months later. The site became operational on 19 July 1999, 16 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 552.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode