Kinmel 1 CIC

Kinmel 1 CIC is an operational 5 MW solar farm in Conwy, generating since 27 June 2016. Planning permission was granted on 11 March 2015, 6 months after submission. Operator of record: Haymaker Energy.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 27 June 2016
Solar Photovoltaics
Technology
Haymaker Energy
Conwy
Authority
Wales

Planning and build timeline

Application submitted27 August 2014
Permission granted11 March 2015
6 months after submission
Operational27 June 2016
16 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Conwy: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Kinmel 1 CIC’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
17.1 km
Landfill Gas · Operational
2.97.5 km
Wind Offshore · Operational
9012.7 km

How big is Kinmel 1 CIC?

Kinmel 1 CIC has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Kinmel 1 CIC?

REPD records the operator as Haymaker Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Kinmel 1 CIC approved and built?

The application was submitted on 27 August 2014. Permission was granted on 11 March 2015, 6 months later. The site became operational on 27 June 2016, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2253.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode